As of March 2025, construction is on schedule and will continue shifting traffic into their final stages over the next several months.

On Friday night March 28th through Saturday night March 29th a High Intensity Construction Cycle (HICC) of the Northbound inner roadway (car lanes) adjacent to Structures 85.77N and 87.10N will have all of the Precast Concrete Construction Barrier (PCCB) removed from the roadway and have the center lane and right lane milled and paved to their final grade.  This will require the closure of the right and center lanes from 8PM on Friday night until approximately 2:00 PM on Saturday afternoon.  All of the truck lanes will be open to both car and truck traffic during this period.

This area will then be restriped to its final alignment (pre-construction alignment) on the night of April 2nd.  Motorists should expect minimal, if any, delays while the shift is taking place.

Milepost 83-85 (Structures 84.24 & 84.55)

  • The four structures are expected to shift into their final stage as follows:

  • Northbound Traffic

    • Structures 84.24N & 84.55N:  May 2025

  • Southbound Traffic

    • Structures 84.24S & 84.55S:  June 2025

Milepost 85-88 (Structure 85.77 & 87.10)

  • The four structures are expected to shift into their final stage as follows:

  • Northbound Traffic

    • Structure 85.77N:  Truck Lanes – Currently in their final alignment.  Final paving dates TBD.

    • Structure 87.10N:  Truck Lanes – Currently in their final alignment.  Final paving dates TBD.

    • Structure 85.77N:  Car Lanes – April 2, 2025

    • Structure 87.10N:  Car Lanes – April 2, 2025

    • Weekend HICC’s will be associated with all of the traffic shifts the weekend prior to the shift date.

  • Southbound Traffic

    • Structure 85.77S:  Truck Lanes - May 2025 (dates TBD)

    • Structure 87.10S:  Truck Lanes - May 2025 (dates TBD)

    • Structure 85.77S:  Car Lanes - May 2025 (dates TBD)

    • Structure 87.10S:  Car Lanes - May 2025 (dates TBD)

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

Read More

As of March 2025, construction is on schedule and will continue shifting traffic into their final stages over the next several months

On Friday night March 21st and Saturday March 22nd a High Intensity Construction Cycle (HICC) of the Northbound outer roadway (truck lanes) adjacent to Structure 87.10N will have all of the Precast Concrete Construction Barrier (PCCB) removed from the roadway and have the left lane and shoulder milled and paved to their final grade. This will require the closure of the left and center lanes from 8PM on Friday night until approximately 4PM on Saturday afternoon.  All of the car lanes will be open to both car and truck traffic during this period.

This area will then be restriped to its final alignment (pre-construction alignment) one night the week of March 24th.  Motorists should expect minimal, if any, delays while the shift is taking place.

Milepost 83-85 (Structures 84.24 & 84.55)

  • The four structures are expected to shift into their final stage as follows:

  • Northbound Traffic

    • Structures 84.24N & 84.55N:  May 2025

  • Southbound Traffic

    • Structures 84.24S & 84.55S:  June 2025

Milepost 85-88 (Structure 85.77 & 87.10)

  • The four structures are expected to shift into their final stage as follows:

  • Northbound Traffic

    • Structure 85.77N:  In its final alignment.  Final paving dates TBD.

    • Structure 87.10N:  Truck Lanes – March 24, 2025

    • Structure 85.77N:  Car Lanes – March 31, 2025

    • Structure 87.10N:  Car Lanes – March 31, 2025

    • Weekend HICC’s will be associated with all of the traffic shifts the weekend prior to the shift date.

  • Southbound Traffic

    • Structure 85.77S:  April 2025 (dates TBD)

    • Structure 87.10S:  April 2025 (dates TBD)

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

Read More

As of November 2024, construction is on schedule and will continue shifting traffic into subsequent stages over the next several months.

The next shift will be off all three lanes of the Northbound inner roadway (car lanes) at Structure 87.10N.  All three lanes will be shifted +/- 24 feet to the left onto the newly constructed bridge deck and will eliminate the existing cattle chute (single lane separated from the other two lanes).  The shift is scheduled for the night of Thursday, November 7th.

Motorists should expect minimal, if any, delays while the shifts are taking place.  The rain date for the traffic shift would be the following week (exact night TBD).

Milepost 83-85 (Structures 84.24 & 84.55)

  • The four structures are expected to shift into Stage 4 as follows:

  • Northbound Traffic

    • Structures 84.24N & 84.55N:  March 2025

  • Southbound Traffic

    • Structures 84.24S & 84.55S:  May 2025

Milepost 85-88 (Structure 85.77 & 87.10)

  • The four structures are expected to shift into Stage 5 (final stage) as follows:

  • Northbound Traffic

    • Structure 85.77N (Stage 5):  Truck Lanes – November 22, 2024 (car lanes were shifted on October 4, 2024)

    • Structure 87.10N (Stage 5):  Car Lanes - November 7, 2024 (truck lanes tentatively scheduled for November 22, 2024)

  • Southbound Traffic

    • Structure 85.77S (Stage 5):  December 2024

    • Structure 87.10S (Stage 5):  December 2024

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

As of September 2024, construction is on schedule and will continue shifting traffic into subsequent stages over the next several months.

The next shift will be off all three lanes of the Northbound inner roadway (car lanes) at Structure 85.77N.  All three lanes will be shifted +/- 24 feet to the left onto the newly constructed bridge deck and will eliminate the existing cattle chute (single lane separated from the other two lanes).  The shift is scheduled for the night of Friday, October 4th.

Motorists should expect minimal, if any, delays while the shifts are taking place.  The rain date for the traffic shift would be the following week (exact night TBD).

Milepost 83-85 (Structures 84.24 & 84.55)

  • The four structures are expected to shift into Stage 4 (final stage) as follows:

  • Northbound Traffic

    • Structures 84.24N & 84.55N:  April 2025

  • Southbound Traffic

    • Structures 84.24S & 84.55S:  June 2025

Milepost 85-88 (Structure 85.77 & 87.10)

  • The four structures are expected to shift into Stage 5 (final stage) as follows:

  • Northbound Traffic

    • Structure 85.77N (Stage 5):  October 4, 2024

    • Structure 87.10N (Stage 5):  November 2024

  • Southbound Traffic

    • Structure 85.77S (Stage 5):  December 2024

    • Structure 87.10S (Stage 5):  December 2024

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

As of September 2024, construction is on schedule and will continue shifting traffic into subsequent stages over the next several months.

The next shift will be off all three lanes of the Southbound inner roadway (car lanes) at Structures 84.24S & 84.55S.  All three lanes will be shifted 40 feet to the left onto the newly constructed bridge deck.  The shift is scheduled for the night of Tuesday, September 17th.

Motorists should expect minimal, if any, delays while the shifts are taking place.  The rain date for the traffic shift would be Wednesday, September 18th.

Milepost 83-85 (Structures 84.24 & 84.55)

  • The four structures are expected to shift into Stage 4 (final stage) as follows:

  • Northbound Traffic

    • Structures 84.24N & 84.55N:  April 2025

  • Southbound Traffic

    • Structures 84.24S & 84.55S:  June 2025

Milepost 85-88 (Structure 85.77 & 87.10)

  • The four structures are expected to shift into Stage 5 (final stage) as follows:

  • Northbound Traffic

    • Structure 85.77N (Stage 5):  November 2024

    • Structure 87.10N (Stage 5):  November 2024

  • Southbound Traffic

    • Structure 85.77S (Stage 5):  December 2024

    • Structure 87.10S (Stage 5):  December 2024

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

As of July 2024, construction is on schedule and will continue shifting traffic into subsequent stages over the next several months.

The next shift will be off all three lanes of the Northbound inner roadway (car lanes) at Structures 84.24N & 84.55N.  All three lanes will be shifted 40 feet to the left onto the newly constructed bridge deck.  The shift is scheduled for the night of Monday, July 22nd.

Motorists should expect minimal, if any, delays while the shifts are taking place.  The rain date for the traffic shift would be Tuesday, July 23rd.

Milepost 83-85 (Structures 84.24 & 84.55)

  • The four structures are expected to shift into Stage 3 as follows:

  • Northbound Traffic

    • Structures 84.24N & 84.55N:  July 15, 2024

  • Southbound Traffic

    • Structures 84.24S & 84.55S:  mid-September 2024

Milepost 85-88 (Structure 85.77 & 87.10)

  • The four structures are expected to shift into Stage 5 (last stage) as follows:

  • Northbound Traffic

    • Structure 85.77N (Stage 5):  September 2024

    • Structure 87.10N (Stage 5):  November 2024

  • Southbound Traffic

    • Structure 85.77S (Stage 5):  November 2024

    • Structure 87.10S (Stage 5):  October 2024


We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

As of June 2024, construction is on schedule and will continue shifting traffic into subsequent stages over the next several months.

The next shift will be the left and center lanes of the Southbound inner roadway (car lanes) at Structure 85.77S.  The two lanes will be shifted 30 feet to the right onto the newly constructed bridge deck.  The shift is scheduled for the night of Thursday, June 20th.

 Motorists should expect minimal, if any, delays while the shifts are taking place.  The rain date for the traffic shift would be Monday, June 24th.

 Milepost 83-85 (Structures 84.24 & 84.55)

  • The four structures are expected to shift into Stage 3 as follows:

  • Northbound Traffic

    • Structures 84.24N & 84.55N:  June 28, 2024

  • Southbound Traffic

    • Structures 84.24S & 84.55S:  mid-September 2024

Milepost 85-88 (Structure 85.77 & 87.10)

  • The four structures are expected to shift into Stage 5 (last stage) as follows:

  • Northbound Traffic

    • Structure 85.77N (Stage 5):  August 2024

    • Structure 87.10N (Stage 5):  November 2024

  • Southbound Traffic

    • Structure 85.77S (Stage 5):  November 2024

    • Structure 87.10S (Stage 5):  October 2024

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

As of May 2024, construction is on schedule and will continue shifting traffic into subsequent stages over the next several months.

 The next shift will be the left and center lanes of the Northbound inner roadway (car lanes) at Structure 87.10N.  The two lanes will be shifted 30 feet to the right onto the newly constructed bridge deck.  The shift is scheduled for the night of Friday June 7th.

 Motorists should expect minimal, if any, delays while the shifts are taking place.  The rain date for the traffic shift would be Monday, June 10th.

Milepost 83-85 (Structures 84.24 & 84.55)

  1. The four structures are expected to shift into Stage 3 as follows:

  2. Northbound Traffic

    1. Structures 84.24N & 84.55N:  mid-July 2024

  3. Southbound Traffic

    1. Structures 84.24S & 84.55S:  mid-September 2024

Milepost 85-88 (Structure 85.77 & 87.10)

  1. The four structures are expected to shift into Stages 4 and 5 as follows:

  2. Northbound Traffic

    1. Structure 85.77N (Stage 5):  August 2024

    2. Structure 87.10N (Stage 5):  November 2024

  3. Southbound Traffic

    1. Structure 85.77S (Stage 4):  end of June 2024

    2. Structure 87.10S (Stage 5):  October 2024

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

As of May 2024 construction is on schedule and will continue shifting traffic into subsequent stages over the next several months. 

The next shift will be the left and center lanes of the Southbound inner roadway (car lanes) at Structure 87.10S.  The two lanes will be shifted 30 feet to the right onto the newly constructed bridge deck.  The shift is scheduled for the night of Wednesday, May 22nd.

Motorists should expect minimal, if any, delays while the shifts are taking place.  The rain date for the traffic shift would be Tuesday, May 28th.

Milepost 83-85 (Structures 84.24 & 84.55)

  1. The four structures are expected to shift into Stage 3 as follows:

  2. Northbound Traffic

    1. Structures 84.24N & 84.55N:  mid-July 2024

  3. Southbound Traffic

    1. Structures 84.24S & 84.55S:  mid-September 2024

Milepost 85-88 (Structure 85.77 & 87.10)

  1. The four structures are expected to shift into Stages 4 and 5 as follows:

  2. Northbound Traffic

    1. Structure 85.77N (Stage 5):  mid-July 2024

    2. Structure 87.10N (Stage 4):  early June 2024

  3. Southbound Traffic

    1. Structure 85.77S (Stage 4):  mid-June 2024

    2. Structure 87.10S (Stage 5):  October 2024

 We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

As of March 2024 construction is on schedule and will continue shifting traffic into subsequent stages over the next several months. 

The next shift will be the left and center lanes of the Northbound inner roadway (car lanes) at Structure 85.77N.  The two lanes will be shifted 30 feet to the right onto the newly constructed bridge deck.  The shift is scheduled for the night of Monday, March 25th.

Motorists should expect minimal, if any delays while the shifts are taking place.  The rain dated for the traffic shift would be Tuesday, March 26th.

 Milepost 83-85 (Structures 84.24 & 84.55)

  • ·The four structures are expected to shift into Stage 3 as follows:

  • Northbound Traffic

    • Structures 84.24N & 84.55N:  mid-July 2024

  • Southbound Traffic

    • Structures 84.24S & 84.55S:  mid-September 2024

  Milepost 85-88 (Structure 85.77 & 87.10)

  • ·The four structures are expected to shift into Stage 4 as follows:

  • ·Northbound Traffic

    • Structure 85.77N (Stage 5):  mid-July 2024

    • Structure 87.10N:  early May 2024

  • ·Southbound Traffic

    • Structure 85.77S:  mid-June 2024

    • Structure 87.10S:  June 2024

 We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

As of November 2023 construction is on schedule and will continue shifting traffic into subsequent stages at five different locations over the next three weeks. 

 The tentative shift schedule is as follows:

1. Structure 87.10 in the Southbound direction.  The outer roadway (truck lanes) on 11/30 and the inner roadway (car lanes) on 12/1.  Shifting from Stage 2 to Stage 3 of five stages.

2. Structure 85.77 in the Northbound direction.  The outer roadway (truck lanes ) on 12/4 and the inner roadway (car lanes) on 12/5.  Shifting from Stage 2 to Stage 3 of five stages.

3. Structures 84.24 & 84.55 in the Southbound direction.  The outer roadway (truck lanes) on 12/7 and the inner roadway (car lanes) on 12/8.  Shifting from Stage 1 to Stage 2 of four stages.

4. Structure 85.77 in the Southbound direction.  The outer roadway (truck lanes) on 12/11 and the inner roadway (car lanes) on 12/12.  Shifting from Stage 2 to Stage 3 of five stages.

5. Structure 87.10 in the Northbound direction.  The outer roadw2ay (truck lanes) on 12/14 and the inner roadway (car lanes) on 12/15.  Shifting from Stage 2 to Stage 3 of five stages.

 Motorists should expect minimal, if any delays while the shifts are taking place.  All of the dates are subject to change based on weather.

 Milepost 83-85 (Structures 84.24 & 84.55)

  • All four structures are expected to shift into Stage 3 in November 2024

  • Northbound Traffic

    • Structures 84.24N & 84.55N

  • Southbound Traffic

    • Structures 84.24S & 84.55S

 Milepost 85-88 (Structure 85.77 & 87.10)

  • All four structures are expected to shift into Stage 4 in May 2024

  • Northbound Traffic

    • Structure 85.77N

    • Structure 87.10N

  • Southbound Traffic

    • Structure 85.77S

    • Structure 87.10S

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

Northbound Outer Roadway (truck lanes) at Structures 84.24 and 84.55

  • All three lanes will be shifted 48 feet to the right onto the newly constructed bridge deck.  The shift is currently scheduled for the night of Wednesday, November 15th and motorists should expect minimal, if any, delays while the shift is taking place. 

Northbound Inner Roadway (car lanes) at Structures 84.24 and 84.55

  • All three lanes will be shifted 48 feet to the right onto what was previously the Outer Roadway (truck lanes).  The shift is currently scheduled for the night of Monday, November 20th and motorists should expect minimal, if any, delays while the shift is taking place. 

Stage 2 traffic shifts are scheduled over the next several months. Please see the Construction Updates page for additional information.

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

Northbound Outer Roadway (Truck Lanes) at Structure 87.10

  • The right two lanes will be shifted 24 feet to the right onto the newly constructed bridge deck.  The shift is currently scheduled for the night of August 24th and motorists should expect minimal, if any, delays while the shift is taking place. 

Stage 2 traffic shifts are scheduled over the next several months. Please see the Construction Updates page for additional information.

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

The next two shifts to occur will be in the Southbound and Northbound Outer Roadways at Milepost 85.77 and are scheduled for July 7th and July 20th, respectively. 

  • Southbound Outer Roadway (truck lanes) at Structure 85.77:

    • The right two lanes will be shifted 24 feet to the left onto the newly constructed bridge deck. The shift is currently scheduled for the night of July 7th and motorists should expect minimal delays, if any, while the shift is taking place. 

  •  Northbound Outer Roadway (truck lanes) at Structure 85.77:

    • The right two lanes will be shifted 24 feet to the right onto the newly constructed bridge deck. The shift is currently scheduled for the night of July 20th and motorists should expect minimal delays, if any, while the shift is taking place.

Stage 2 traffic shifts are scheduled over the next several months. Please see the Construction Updates page for additional information.

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

Stage 2 Traffic Shifts

Stage 2 traffic shifts are scheduled over the next several months. Please see the Construction Updates page for additional information.

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

Occasional Daily & Nightly Lane Closures as needed.

No Planned Traffic Shifts until Stage 1 Completion.

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

New Traffic Pattern for the Northbound and Southbound Truck and Car Lanes between Interchanges 9 and 10 starting the week of October 31st

WOODBRIDGE, NJ - A new stage of bridge deck reconstruction and roadway improvements will occur in the Northbound and Southbound Truck and Car lanes of the New Jersey Turnpike between Milepost 85 to Milepost 88 (between Interchange 9 and Interchange 10). 

Northbound

All three of the Northbound Inner (car) traffic lanes will be shifted to the left.  The Northbound Outer (truck) traffic will be split with two lanes to the right of the new workzone and one lane to the left of the new workzone.  These shifts are scheduled to be implemented over several nights the week of 10/31/22 & 11/7/22.  The lanes are scheduled to be in this configuration until May 2023.

Southbound

All three of the Southbound Inner (car) traffic lanes will be shifted to the left.  The Southbound Outer (truck) traffic will be split with two lanes to the right of the new workzone and one lane to the left of the new workzone.  These shifts are scheduled to be implemented over several nights the week of 11/14/22.  The lanes are scheduled to be in this configuration until June 2023.

 It is anticipated that traffic impacts will be light to moderate during night time hours.

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

New Traffic Pattern for the Northbound and Southbound Truck and Car Lanes between Interchanges 9 and 10 starting September 15th

WOODBRIDGE, NJ - A new stage of bridge deck reconstruction and roadway improvements will occur in the Northbound and Southbound Truck and Car lanes of the New Jersey Turnpike between interchange 9 and interchange 10 (Milepost 83.3 to 88.1).  The new traffic pattern will shift each of the four roadways left to create a workzone on the right sides of the Turnpike.  Each of the four roadways will be shifted on separate nights starting on Wednesday Night September 14th at 6:00PM and continue with nightly closures until all four roadways are shifted.  It is expected to take between four to six nights to complete the shifts (9/14, 9/15, 9/16, 9/19, 9/20 & 9/21).

It is anticipated that traffic impacts will be light to moderate during night time hours.

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

Northbound Construction between interchanges 9 and 10 from June 24th to June 27th

WOODBRIDGE, NJ - A stage of bridge deck reconstruction and roadway improvements will occur in the Northbound direction of the New Jersey Turnpike between interchange 9 and interchange 10 (Milepost 83.3 to 88.1) starting on Friday Night June 24th at 6:00PM and lasting until Monday Morning June 27th at 5:00AM. The Northbound outer lanes (truck lanes) will be reduced from their existing three lanes to one or two lanes over the course of the weekend.  Two lanes of traffic will be open during the primarily daytime hours (7:00 AM until midnight) and only one lane of traffic will be open during the primarily nighttime hours:

·        9:00 PM Friday night until 7:00 AM on Saturday morning

·        Midnight on Saturday night until 07:00 AM Sunday morning

·        Midnight on Sunday night until 06:00 AM Monday morning.

 

It is anticipated that traffic impacts will be moderate during peak hours. Drivers should allow additional travel time this weekend.

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.

Northbound Construction between interchanges 9 and 10 from June 17th to June 20th

WOODBRIDGE, NJ - A stage of bridge deck reconstruction and roadway improvements will occur in the Northbound direction of the New Jersey Turnpike between interchange 9 and 10 (Milepost 83.3 to 88.1) starting on Friday Night June 17th at 8:00PM and lasting until Monday Morning June 20th at 6:00AM. Over the period of night the Northbound Inner roadway will be closed from 8:00PM to 6:00AM and during the day time hours it will be reduced to two lanes of travel.

It is anticipated that traffic impacts will be moderate during peak hours. Drivers should allow additional travel time this weekend.

We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.