As of July 2024, construction is on schedule and will continue shifting traffic into subsequent stages over the next several months.

The next shift will be off all three lanes of the Northbound inner roadway (car lanes) at Structures 84.24N & 84.55N.  All three lanes will be shifted 40 feet to the left onto the newly constructed bridge deck.  The shift is scheduled for the night of Monday, July 22nd.

Motorists should expect minimal, if any, delays while the shifts are taking place.  The rain date for the traffic shift would be Tuesday, July 23rd.

Milepost 83-85 (Structures 84.24 & 84.55)

  • The four structures are expected to shift into Stage 3 as follows:

  • Northbound Traffic

    • Structures 84.24N & 84.55N:  July 15, 2024

  • Southbound Traffic

    • Structures 84.24S & 84.55S:  mid-September 2024

Milepost 85-88 (Structure 85.77 & 87.10)

  • The four structures are expected to shift into Stage 5 (last stage) as follows:

  • Northbound Traffic

    • Structure 85.77N (Stage 5):  September 2024

    • Structure 87.10N (Stage 5):  November 2024

  • Southbound Traffic

    • Structure 85.77S (Stage 5):  November 2024

    • Structure 87.10S (Stage 5):  October 2024


We encourage drivers to check traffic conditions in the area with these resources:

· New Jersey 511. Call from any hands-free device. Follow the prompts to ask for traffic conditions on the New Jersey Turnpike.
· Traffic cameras. Visit the NJTA website or the New Jersey 511nj website to see live views of traffic in the area.
· SafeTripNJ. Download this app on your Apple or Android device for hands-free, eyes-free traffic alerts in the project area.