As of November 2023 construction is on schedule and will continue shifting traffic into subsequent stages at five different locations over the next three weeks. 

 The tentative shift schedule is as follows:

1. Structure 87.10 in the Southbound direction.  The outer roadway (truck lanes) on 11/30 and the inner roadway (car lanes) on 12/1.  Shifting from Stage 2 to Stage 3 of five stages.

2. Structure 85.77 in the Northbound direction.  The outer roadway (truck lanes ) on 12/4 and the inner roadway (car lanes) on 12/5.  Shifting from Stage 2 to Stage 3 of five stages.

3. Structures 84.24 & 84.55 in the Southbound direction.  The outer roadway (truck lanes) on 12/7 and the inner roadway (car lanes) on 12/8.  Shifting from Stage 1 to Stage 2 of four stages.

4. Structure 85.77 in the Southbound direction.  The outer roadway (truck lanes) on 12/11 and the inner roadway (car lanes) on 12/12.  Shifting from Stage 2 to Stage 3 of five stages.

5. Structure 87.10 in the Northbound direction.  The outer roadw2ay (truck lanes) on 12/14 and the inner roadway (car lanes) on 12/15.  Shifting from Stage 2 to Stage 3 of five stages.

Motorists should expect minimal, if any delays while the shifts are taking place.  All of the dates are subject to change based on weather.

 Milepost 83-85 (Structures 84.24 & 84.55)

  • All four structures are expected to shift into Stage 3 in November 2024

  • Northbound Traffic

    • Structures 84.24N & 84.55N

  • Southbound Traffic

    • Structures 84.24S & 84.55S

 Milepost 85-88 (Structure 85.77 & 87.10)

  • All four structures are expected to shift into Stage 4 in May 2024

  • Northbound Traffic

    • Structure 85.77N

    • Structure 87.10N

  • Southbound Traffic

    • Structure 85.77S

    • Structure 87.10S