As of November 2023 construction is on schedule and will continue shifting traffic into subsequent stages at five different locations over the next three weeks.
The tentative shift schedule is as follows:
1. Structure 87.10 in the Southbound direction. The outer roadway (truck lanes) on 11/30 and the inner roadway (car lanes) on 12/1. Shifting from Stage 2 to Stage 3 of five stages.
2. Structure 85.77 in the Northbound direction. The outer roadway (truck lanes ) on 12/4 and the inner roadway (car lanes) on 12/5. Shifting from Stage 2 to Stage 3 of five stages.
3. Structures 84.24 & 84.55 in the Southbound direction. The outer roadway (truck lanes) on 12/7 and the inner roadway (car lanes) on 12/8. Shifting from Stage 1 to Stage 2 of four stages.
4. Structure 85.77 in the Southbound direction. The outer roadway (truck lanes) on 12/11 and the inner roadway (car lanes) on 12/12. Shifting from Stage 2 to Stage 3 of five stages.
5. Structure 87.10 in the Northbound direction. The outer roadw2ay (truck lanes) on 12/14 and the inner roadway (car lanes) on 12/15. Shifting from Stage 2 to Stage 3 of five stages.
Motorists should expect minimal, if any delays while the shifts are taking place. All of the dates are subject to change based on weather.
Milepost 83-85 (Structures 84.24 & 84.55)
All four structures are expected to shift into Stage 3 in November 2024
Northbound Traffic
Structures 84.24N & 84.55N
Southbound Traffic
Structures 84.24S & 84.55S
Milepost 85-88 (Structure 85.77 & 87.10)
All four structures are expected to shift into Stage 4 in May 2024
Northbound Traffic
Structure 85.77N
Structure 87.10N
Southbound Traffic
Structure 85.77S
Structure 87.10S