As of February, 2023 Construction is on schedule and is within Stage 1 of 5 alignment of the overall contract as follows:

Milepost 83-85 (Structure 84.24 & 84.55)

· Northbound Traffic on both the inner and outer roadways is shifted to the left to create a work zone on the right side of the bridge structures. Northbound Stage 1 completion date tentatively scheduled for the end of June 2023.

· Southbound traffic on both the inner and outer roadways is shifted to the left to create a work zone on the right side of the bridge structures. Southbound Stage 1 completion date tentatively scheduled for the end of September 2023

Milepost 85-88 (Structure 85.77 & 87.10)

· Northbound Traffic on both the inner and outer roadways is shifted to the left to create a work zone on the right side of the  bridge structures. Northbound Stage 1 completion date tentatively scheduled for the end of June 2023.

· Southbound traffic on the inner roadway is shifted left to allow for the outer roadway divided with one lane to the left and two lanes to the right to create a work zone between the active travel lanes at each bridge structures. All Lanes proceed thru work zone. Southbound Stage 1 completion date tentatively scheduled for the end of May 2023