Stage 1 Traffic Shifts from Milepost 83 to Milepost 85
As of September 30, 2022 the two structures at milepost 84.24 and 84.55 have been shifted into their Stage 1 alignment as follows:
· Northbound Traffic on both the inner and outer roadways was shifted to the left (West) to create a workzone on the right (East) side of the structures. Northbound Stage 1 completion date tentatively scheduled for the end of June 2023.
· Southbound traffic on both the inner and outer roadways was shifted to the left (East) to create a worzkone on the right (West) side of the structures. Southbound Stage 1 completion date tentatively scheduled for the end of August 2023.