Northbound Inner and Northbound Outer Lane Shifts (Pre-Stage 1A)

April 1, 2022

The shoulders in the project area are being reconstructed. Concrete construction barriers are being placed between the inner and outer roadways on both the northbound and southbound sides. Guiderails and sign structures are being removed. This phase of construction, which is known as “Pre-Stage 1A,” is scheduled to continue into May. In order to minimize impacts on motorists, this construction is being done at night.

May 1, 2022

The reconstruction of the shoulders in the project area continues. This work is scheduled to be completed in May. Once complete, the project will shift to a new phase, “Pre-Stage 1B,” which is scheduled to continue until July. In order to minimize impacts on motorists, this construction is being done at night.

May 11, 2022

The New Jersey Turnpike SNI & SNO Roadways, Northbound Inner and Northbound Outer, respectively, will be shifted starting at MP 83.90, with a lane shift (SNO onto the Right Shoulder & SNI onto the Left Shoulder) through MP 84.55, from Monday, May 16th at 8 PM to Wednesday, July 6th at 8 PM to allow for pre-construction work to be performed to multiple bridge deck replacements. This work is expected to last Seven (7) weeks. In the event of inclement weather, this work will be rescheduled for a different date. The New Jersey Turnpike SNI & SNO Roadways, Northbound Inner and Northbound Outer, respectively, will be shifted starting at MP 83.90, with a lane shift (SNO onto the Right Shoulder & SNI onto the Left Shoulder) through MP 84.55, from Monday, May 16th at 8 PM to Wednesday, July 6th at 8 PM to allow for pre-construction work to be performed to multiple bridge deck replacements. This work is expected to last Seven (7) weeks. In the event of inclement weather, this work will be rescheduled for a different date.